History
'05 Pulley
Results
(more info coming soon!)
| |
|
Team: High Entropy |
| |
|
| |
|
Team: The Bulgarians: "Otbor
Unaci" |
| |
|
| |
|
Team: Mr. CD |
| |
|
| |
|
Team: Taking Back Sunday "TBS" |
|
|
| |
|
Team: #1 |
|
|
|
'04 Ramp
Results
There were a total of six teams competing for two
criterion: Maximum Departure Velocity and Maximum Transit Time.
For this competition, teams were allowed to use kite string as an additional
component to their structure. There was no limit to the length of string
used (the string did however, have to have a strength comparable to ordinary
kite string). The completed structure could have a mass no greater than
two kilograms (which is about 250 CD's).
 |
 |
Team: Acacia and
ΔZ |
| Originally targeting first place finishes in
each category, Acacia and ΔZ learned
quickly how difficult building a multiple function structure can be.
Their efforts paid off in the end, however. This team placed second
in Maximum Departure Velocity (1.93m/s) and third in Maximum Transit Time
(4.21s). |
|
 |
|
Team: Bonus Points |
| Together with spirit and the common motivation
for earning bonus points in General Physics, this team was eager to apply
physics principles to their design. With more time to put their
ideas into production, we're sure they would have found more success.
Unfortunately, time was not on their side for this competition! |
|
 |
 |
Team: High Entropy |
| Don't let the name of this team fool you; there
was a lot of organization and planning that had taken place for their
structure. With a very long ramp and numerous strategically placed
"speed bumps" along the way, High Entropy was the clear winner in the
Maximum Transit Time category (8.88s). |
|
 |
|
Team: PHAT and Chicks |
| With a name like PHAT and Chicks, we thought
for sure there would be some creativity in design! Unfortunately,
their structure did not take a final form to place in either of the
categories for the CD Ramp competition. Maybe next year! |
|
| |
|
Team: Phi Lambda Chi |
| Phi Lambda Chi's ramp was what one might call a
"low rider." Low to the floor and piecemeal design, this ramp placed
second in the Maximum Transit Time (6.46s) and third in the Maximum
Departure Velocity (0.97s). |
|
 |
|
Team: The Bulgarians |
| The Bulgarians had one goal in mind and put all
of their design efforts to one category. And it paid off!
Constructing the shortest ramp structure with the steepest incline, they
easily took first place in the Maximum Departure Velocity category
(2.06m/s). |
'03 Bridge
Results
There were a total of five teams competing for three
criterion: Greatest Load-Bearing Capacity, Greatest Horizontal Span,
and
Greatest Vertical Clearance. For this competition, teams were
allowed to use kite string as an additional component to their structure.
There was no limit to the number of CD's used or on the length of string used
(the string did however, have to have a strength comparable to ordinary kite
string).
 |
 |
Team: It Doesn't Matter |
| Team It Doesn't Matter came with a plan
to win both the greatest vertical span and greatest horizontal clearance
categories. Veterans of the CD Challenge, this team quietly began
construction early in the competition far away from the other teams.
Their strategy and hard work resulted in a bridge that won the greatest
vertical clearance (41.25"). |
|
 |
 |
Team: Midget Monkies |
| New to the CD Challenge, the Midget Monkies
were hard at work for most of the day. As the competition drew
to a close and the other bridges had taken form, these enthusiastic
teammates secretly dismantled their bridge so we couldn't get a picture of
the final construction! These teammates, were however, very good
sports and remained on site cheering for the other teams as the judging
was completed. |
|
 |
 |
Team: Shockers |
| The Shockers were returning to the CD
Challenge this year with a determination to win the greatest horizontal
span category. Their modification of the CD's was one that was not
at all expected by anyone familiar with the CD Challenge! Had the
rules allowed for mid section support piers in judging this category,
their final span would have been at least tripled. They won the
maximum horizontal clearance category by over 40" (for a total of
182.75"). |
|
 |
 |
Team: Check Out Our Load |
| Team Check Out Our Load brought to the
table their CD's, cutting utensils, and ambition--all without a plan!
But before too long, a strategy had been developed to target the category
no other team had yet begun working on: the maximum load-bearing capacity.
Supported by strong piers and making good use of extra CD's a
counter-weights, their bridge supported most of gram masses available but
eventually collapsed at 3.6 kilograms. |
|
 |
 |
Team: Adrenergic Catecholamines |
| Despite the length of their team name, the
Adrenergic Catecholamines were not competing for the greatest
horizontal span! This team demonstrated what can be accomplished
with an indefinite supply of resources. Using well over 100
unmodified CD's and more than a full spool of kite string, this team's
bridge supported a load over 18 kilograms. It's true limit was not
determined due to a lack of kilogram masses--although it did successfully
support one of the judge's children! |
|
|
'01 Tower
Results
For our debut competition (fall '01) the
challenge was to build a CD Tower. There were a total of six teams
competing for four criterion: Tallest Tower, Most Creative Design,
Height to Mass Ratio, and the fourth criterion, grand prize, being a
composite weighted scoring of the first three criterion.
 |
 |
Team: Bob the Builders |
| If there were metals awarded for effort and
perseverance,
Bob the Builders would have taken home the gold! Their
design was a good one, and took second place in the height to mass
ratio criteria (0.78cm/g). Team members learned not all CD's are
created equally, and that scissor quality is important! |
|
 |
 |
Team: goforthandclick |
| Off to an early start, goforthandclick
established quick earned respect from on-lookers because of their intricate modular design (pictured to the
left). The fittings proved to be too tight causing important
pieces to break, ultimately sending these CD
structural engineers back to the drawing board. The team showed up
just prior to the end of the event to prop up their height to mass
ratio (11cm/g) award winning "tower." Because the value
obtained for this criterion was so skewed to their favor (89% of
weighted points), this team won the grand prize even though they
had the shortest tower (11cm)! |
|
 |
 |
Team: Dremel |
| Having worked on their CD's with a Dremel tool
before arriving on site, Dremel's tower showed much promise as
time continued on. In fact, had there been more time to solve
stability issues, this team would have most likely won the tallest
tower award because of the modular component design (128cm). |
|
 |
 |
Team: Delta Zeta |
| Full of spirit, Delta Zeta came to the
event with a pair of scissors and put a lot of heart into their tower(s).
After deciding their tower's design had a height limit shorter than
their competitors', this team disassembled their tower to start from
scratch (again!). We are certain to see their determination
demonstrated in future CD Challenges! |
|
 |
 |
Team: If All Else Fails |
| Holding true to their name, If All Else
Fails quietly built their tower without a plan while observing the
progress of the other teams. As their pyramid-shaped tower reached
its height's physical limit, they crossed their fingers in hopes that
time would expire before the other competitors' towers were
completed. It worked! They won the tallest tower
award (165cm). |
|
 |
 |
Team: SPS |
| To capitalize on the creative components
criterion, SPS structured their tower's design to resemble a
Christmas tree. As part of their construction, swaying limbs of CD's,
a maximum horizontal span, and a star topping the structure earned them the creative
design award. They used every single one of the provided 100
CD's in their tower to arrive at a symmetrical finished product! |